Works Notice - Yanks Jetty Restoration

Update on Yanks Jetty 20th August 2013

We refer to the notification issued on 14 June 2013 regarding restoration works planned for Yanks Jetty. We are pleased to inform you that the work is now substantially complete and the Jetty is again open to mariners and the public. Further minor work will be conducted in the coming six weeks, however this will not result in closure of the Jetty.

This work is being delivered under the Natural Disaster Relief and Recovery Arrangements (NDRRA) program; a joint federal (75%) and state (25%) government initiative.

Yanks Jetty was restored as part of the NDRRA program where Hinchinbrook Shire Council has partnered with AECOM to repair and restore local infrastructure in the region following damage caused by severe weather events in 2011 and 2012.

If you have any queries regarding the restoration works being undertaken, please call the project hotline on 1800 246 612 or email hscndrra@aecom.com.

AECOM and Hinchinbrook Shire Council would like to thank you for your cooperation and patience as we work together to restore the Hinchinbrook region.

From the program team



Please see the following release regarding the restoration of Yanks Jetty.

Hinchinbrook Shire Council has partnered with AECOM to repair and restore local infrastructure in the region following damage caused by severe weather events in 2011 and 2012. Additional repair work is also required after the recent January 2013 flood. This work is being delivered under the Natural Disaster Relief and Recovery Arrangements (NDRRA) program; a joint federal (75%) and state (25%) government initiative.

Yanks Jetty is being restored as part of the NDRRA program.

Construction is due to commence on the Orpheus Island site from Monday, 8 July 2013. All environmental and other approvals have been sought and have been issued. Construction is anticipated to be completed by Friday 16 August 2013, weather permitting.

Restoration of the Jetty will take about 12 weeks to complete. Work has already begun off site on the pre- fabrication of the new Jetty. From late July, work will begin on site and is scheduled to last between two, to four weeks, depending on the weather.

Work on site will involve the removal of the existing Jetty and installation of a new Jetty. The Jetty will be closed and out of bounds for community use during this period: 8 July – 16 August 2013.

The pontoon will remain in place during the works period, although mariners and the community will not be able to use the facilities during the construction period.

Every effort will be made to minimise inconvenience and provide information to stakeholders on work in progress.

Please note that construction timetables can be subject to change. Up to date information will be provided in the Notice to Mariners. If you have any queries regarding the restoration works being undertaken, please call the project hotline on 1800 246 612 or email hscndrra@aecom.com

Your safety and the safety of our works team are most important. Please respect the construction zone and follow any signage. AECOM and Hinchinbrook Shire Council would like to thank you for your cooperation and patience as we work together to restore the Hinchinbrook region.

From the program team.